"Brick street rehabilitation slated to start next week" This Week News

Link: Brick street rehabilitation slated to start next week
David J. Cross
This Week News
June 25, 2008

German Village residents can expect to see crews marking and working on brick streets next week.

Barring poor weather, contractors are expected to start the city's brick street rehabilitation project July 8. The contract is with G&G Concrete Construction.

"What the people will see is we will be going out and putting markings down on the brick," said Mary Carran Webster, Columbus' assistant public service director. "It doesn't necessarily mean they are digging up the whole road."...

...There are 32 miles of brick streets in the city and German Village will be the first area worked on. Webster estimated the entire cost of the program will be about $200,000...

Posted by Paul Bonneville on June 30, 2008 | Permalink